Allston, MA
Harvard University Science Complex, MWRA Sewer
Scope/Solutions
Harvard University planned to locate a new science complex above a Massachusetts Water Resources Authority (MWRA) brick masonry pipeline that was over 115 years old. The University was concerned about the impact of construction on the 69 in. high by 62 in. wide active masonry sewer. SGH studied the potential effects of ground displacement that can distort and increase soil loads on buried structures, construction traffic live loads, surface vibrations, and impacts from falling objects.
Highlights of SGH’s work to assess pipeline response to construction-induced vibration and movement include the following:
- Examined the sequences of both Boston blue clay excavation and installation and tensioning of a tie-back system
- Used ABACUS Explicit to develop three-dimensional soil-structure interaction models
- Analyzed stress-wave propagation through the soil
- Assessed the extent of ground displacement
- Modeled construction of the slurry wall adjacent to the pipe using nonlinear finite-element soil-structure interaction analysis
- Used different nonlinear soil models, such as Mohr-Coulomb in ABAQUS, to simulate the soil layers, buried and above-grade structures, and construction processes
- Collaborated with the owner, contractor, and other consultants, enabling Harvard to proceed with the project without endangering the pipeline
To minimize impact, the design of the four-building research complex wraps around the pipeline.
Project Summary
Solutions
Repair & Rehabilitation
Services
Advanced Analysis
Markets
Infrastructure & Transportation
Client(s)
Sea Consultants, Inc.
Specialized Capabilities
Buried Infrastructure | Computational Mechanics
Key team members
Additional Projects
Northeast
99 Summer Street Parking Garage
The parking garage, constructed with concrete slabs on metal deck supported by steel beams and columns, includes two below-grade levels under a twenty-story office building. SGH performed a condition assessment and designed repairs to extend the useful life of the parking structure.
Northeast
MBTA Bus Repair Garage
The building includes three garage bays, offices, and locker facilities for the bus operators and repair staff. When an elevated concrete floor slab in one of the bays failed under the weight of a bus wheel, the MBTA retained SGH to investigate.