Chicago, IL

325 North Ashland Avenue

Scope/Solutions

The 80,000 sq ft building in Chicago’s Fulton Market neighborhood was constructed in the early 1950s as a manufacturing facility. Potential buyers were considering redeveloping the property for use as office space or a data center, and the owner wanted to evaluate the feasibility of adding two occupiable levels (a floor and roof deck) to the existing cast-in-place concrete structure. SGH evaluated the existing structure’s ability to support the proposed vertical addition and proposed strengthening concepts for the gravity- and lateral-load-resisting systems.

Using original drawings, building operations records, and improvement logs to determine the existing configuration, SGH evaluated the structure’s ability to support the new loads associated with adding the two new levels. We developed conceptual design options for the following:

  • Supporting the new occupiable floor on the existing roof by either strengthening the concrete slab with new steel plates or adding a floor overbuild
  • Supplementing the lateral-load-resisting system to accommodate new loads from the vertical expansion

We presented these concepts in a feasibility study report prepared for the owner and potential buyers to obtain order-of-magnitude pricing.

Project Summary

completion-date

2018

Completion Date
Solutions
New Construction | Repair & Rehabilitation
Services
Structures
Markets
Commercial | Industrial
Client(s)
Transwestern | Rickard Circular Folding Company
Specialized Capabilities
Building Design | Repair & Strengthening

Key team members

Connor Bruns
Connor Bruns
Senior Project Manager