The five-story building at 135 Franklin Street experienced damage due to settlement. Over the years, the owner undertook repairs at the elevator pit and central corridors and needed to address problems at a basement condominium. SGH investigated the cause of the issues and designed repairs.
SGH investigated settlement at the concrete building founded on pile-supported grade beams around the building perimeter and at certain interior walls. Highlights of our work include the following:
- Investigated the cause of the settlement using test borings and a test pit through the basement level slab, which is supported by soil subgrade and grade beams
- Researched pertinent drawings and construction records at Town Hall
- Developed remedial concepts and prepared cost estimates for the owner’s consideration
- Designed a replacement slab capable of accommodating future settlement
- Performed construction administration services, including reviewing contractor submittals and requests for information, observing ongoing construction, and helping resolve field issues
Project Summary
Solutions
Repair & Rehabilitation
Services
Structures
Markets
Residential
Client(s)
Northeast Real Estate Advisors, Inc.
Key team members
Additional Projects
Northeast
The Savoy
SGH was the structural engineer for the project, which involved demolition of the existing building and preservation of the two facades that face the historic district.
Northeast
Cambridgeport Commons
The Cambridgeport Commons Condominium complex consists of seven buildings over a below-grade parking garage. SGH investigated the cause of leakage and developed repair options.