Stoneham, MA
135 Franklin Street
Scope/Solutions
The five-story building at 135 Franklin Street experienced damage due to settlement. Over the years, the owner undertook repairs at the elevator pit and central corridors and needed to address problems at a basement condominium. SGH investigated the cause of the issues and designed repairs.
SGH investigated settlement at the concrete building founded on pile-supported grade beams around the building perimeter and at certain interior walls. Highlights of our work include the following:
- Investigated the cause of the settlement using test borings and a test pit through the basement level slab, which is supported by soil subgrade and grade beams
- Researched pertinent drawings and construction records at Town Hall
- Developed remedial concepts and prepared cost estimates for the owner’s consideration
- Designed a replacement slab capable of accommodating future settlement
- Performed construction administration services, including reviewing contractor submittals and requests for information, observing ongoing construction, and helping resolve field issues
Project Summary
Solutions
Repair & Rehabilitation
Services
Structures
Markets
Residential
Client(s)
Northeast Real Estate Advisors, Inc.
Key team members
Additional Projects
Northeast
New Hope Community/Woodland Terrace Revitalization
SGH was the structural engineer of record and was selected in part due to our knowledge of and experience with Optimum Value Engineering (OVE), although ultimately the developer elected to utilize standard wood framing details.
Northeast
Post-Hurricane Sandy Evaluations
On 29 October 2012, Hurricane Sandy made landfall along the eastern United States seaboard, bringing high winds and a tidal surge, and causing billions of dollars in damage to our built environment. Some of the worst damage was reported in the coastal areas of New York and New Jersey.